Brief Description: Replacement of 5513 due to numerous problems which led to network degradation. A new 4500 will take its place.
Note: All times shown here is Bangkok Time.
Detail Description: Before the Cutover:
- Pre-configure the 4500 switch. Ports should be on vlan 15(116.40.193.0/24). Must follow NST guides.
- Assign 116.40.193.5 as MNGT IP.
- Test DHCP of PC when connected to the port
- Burn in test.
Cutover:
- Shutdown 5513.
- Clear out un-necessary cables on the cabinet.
- Mount the 4500
- Check connectivity with the core switch.
- Try getting IP address from DHCP server
Impact: - No Network Connectivity to Floor 15. Users are asked to move to other floors during the activity.
Resources Impacted: THBKKSL4-5513
Action / description | Who | What is deliverable? | Status | |
1 | Prep | |||
1.1 | Assign IP address | Local-IT | Fri 7 Sep 2007 (116.40.193.5 for testing and change it back to 116.40.193.4 when we completed configuration ) | DONE |
1.2 | Drawing | Regional | ||
1.3 | Pre-configure and connect to network | Local-IT | Monday, September 10, 2007 inform to Regional | DONE |
1.4 | Configuration | Regional | Tuesday, September 11, 2007 | |
1.5 | Prepare CEMS Change | Regional | Tuesday, September 11, 2007 | DONE |
1.6 | Outage announcement | Local-IT | Tuesday, September 11, 2007 | DONE |
1.7 | Testing the switch before cutover | Regional | Friday, September 14, 2007 | DONE |
2 | Actual Cutover | Saturday, September 15, 2007 08:30 a.m. to 05:00 pm |
||
2.1 | Cabling | Local-IT | 8:30 am – 01:00 pm. | |
2.2 | Physical Replace the switch | Local-IT | 01:00 pm – 03:00 pm. | |
2.3 | Testing 2.3.1 Soft Test 2.3.2 Physical Test (end user point signal check) |
Regional Local-IT |
03:00 pm – 05:00 pm. | |
3 | Post Install | |||
3.1 | Documentation | Regional | ||
3.2 | Config revisions | Regional | ||
3.3 | CEMS enrollment | Regional |
Detail Description: Before the Cutover:
- Pre-configure the 4500 switch. Ports should be on vlan 15(116.40.193.0/24). Must follow NST guides.
- Assign 116.40.193.5 as MNGT IP.
- Test DHCP of PC when connected to the port
- Burn in test.
Cutover:
- Shutdown 5513.
- Clear out un-necessary cables on the cabinet.
- Mount the 4500
- Check connectivity with the core switch.
- Try getting IP address from DHCP server
Impact: - No Network Connectivity to Floor 15. Users are asked to move to other floors during the activity.
Resources Impacted: THBKKSL4-5513